News

Bus Stop Construction on Southside July 20-21, 2021

July 20, 2021

GRTC News

Bus Stop Construction
New concrete landing pads are being built at select stops on Southside.

WHEN: July 20-21, 2021.

WHAT: GRTC is constructing new concrete landing pads at the following bus stops on Southside to improve access for passengers according to the Americans with Disabilities Act. These landing pads provide a stable and smooth surface for passengers to board and alight, including using the bus ramp that can deploy levelly onto the pad.

IMPACT: These bus stops are temporarily closed during construction, with temporary alternate bus stops open nearby.Southside bus stop map for TAP work

July 20 (Area 1)

#247 – Belt Boulevard at 141

#604 – Carnation & Midlothian

#607 – Carnation & Warwick

#813 – Crutchfield at George Wythe High School Track

#932 – Forest Hill & Bliley

#978 – Forest Hill & Roanoke

#1375 – Jahnke & St John’s Wood

#1757 – Midlothian & Erich

#2112 – Roanoke & Moody

#2474 – Giant at 110

#2493 – Midlothian at Overland Transportation

July 21 (Area 2)
#303 – Southwood & Clarkson

#311 – Broad Rock & Southall

#313 – Broad Rock at 3309

#761 – Clarkson & Margrave

#775 – Commerce & Bells

#1273 – Hull & 24th

#1320 – Hull & Warwick

#1431 – Jefferson Davis & Stockton

#1437 – Jefferson Davis & Walmsley

#2148 – Ruffin at Ruffin Apartments

(Area 3 was previously completed)

Download