New concrete landing pads are being built at select stops on Southside.

WHEN: July 20-21, 2021.

WHAT: GRTC is constructing new concrete landing pads at the following bus stops on Southside to improve access for passengers according to the Americans with Disabilities Act. These landing pads provide a stable and smooth surface for passengers to board and alight, including using the bus ramp that can deploy levelly onto the pad.

IMPACT: These bus stops are temporarily closed during construction, with temporary alternate bus stops open nearby.Southside bus stop map for TAP work

July 20 (Area 1)

#247 - Belt Boulevard at 141

#604 - Carnation & Midlothian

#607 - Carnation & Warwick

#813 - Crutchfield at George Wythe High School Track

#932 - Forest Hill & Bliley

#978 - Forest Hill & Roanoke

#1375 - Jahnke & St John's Wood

#1757 - Midlothian & Erich

#2112 - Roanoke & Moody

#2474 - Giant at 110

#2493 - Midlothian at Overland Transportation

July 21 (Area 2)
#303 - Southwood & Clarkson

#311 - Broad Rock & Southall

#313 - Broad Rock at 3309

#761 - Clarkson & Margrave

#775 - Commerce & Bells

#1273 - Hull & 24th

#1320 - Hull & Warwick

#1431 - Jefferson Davis & Stockton

#1437 - Jefferson Davis & Walmsley

#2148 - Ruffin at Ruffin Apartments

(Area 3 was previously completed)